Menu: SPRO -> Production -> Material Requirements Planning -> Planning -> Scheduling and Capacity Parameters -> Define Floats (Scheduling Margin Key)
Create a new entry and define the parameters. Here is the definition:
Opening period - Number of workdays subtracted from the order start date to determine the creation date. The opening period can be used by the MRP controller as an extra time buffer. The opening period is only used in backward scheduling.
Float before - The number of working days between the order start date and the scheduled start date; used as a float in production scheduling.
Float After - The number of working days used as a float for scheduling between the order due date and the scheduled finish date. The safety margin after production is used for compensating malfunctions within the order production.
Release Period - Number of working days in the release period of this order.
Showing posts with label MRP. Show all posts
Showing posts with label MRP. Show all posts
How to create MRP controllers in SAP
Menu: SPRO -> IMG -> Production -> Material Requirements Planning -> Master Data -> Define MRP Controllers
How to see MRP views in material master in SAP
Run transaction MM02 and select the view that you want to see. In case the MRP views are not available for selection, it may mean that the material has not yet been extended to the selected plant. To do this, run MM01 and type the material number. Then select the MRP views. You will be asked to add a few mandatory fields. After saving, the views will be available in MM02.
Transaction: MM01 and MM02
Transaction: MM01 and MM02
Subscribe to:
Posts (Atom)